All annual project reports
1903 records found
| Project name | Year | Dept | DCA (RAG) | Start Date | End Date | Base £m | Fcast £m | Variance % | WLCost £m |
|---|---|---|---|---|---|---|---|---|---|
| A400M | 2018 | MOD | Amber | 2000-05-17 | 2023-03-31 | 173.39 | 123.76 | -29.00% | 3,519.16 |
| A400M | 2019 | MOD | Amber | 2000-05-17 | 2023-03-31 | 118.42 | 95.29 | -20.00% | 3,394.89 |
| A400M | 2020 | MOD | Amber | 2000-05-17 | 2024-03-31 | 197.82 | 186.19 | -0.06% | 3,356.23 |
| A400M | 2021 | MOD | Amber | 2000-05-17 | 2024-03-31 | 191.48 | 181.44 | -5.00% | 3,783.03 |
| A400M | 2022 | MOD | Amber | 2000-05-17 | 2024-03-31 | 214.19 | 153.67 | -28.00% | 3,802.00 |
| A400M | 2023 | MOD | Amber | 2000-05-17 | 2024-03-31 | 228.41 | 210.56 | -8.00% | 3,817.00 |
| A417 Air Balloon | 2021 | DFT | Amber/Green | 2015-04-01 | 2025-06-30 | 17.41 | 17.82 | 2.00% | 0.00 |
| A417 Air Balloon | 2022 | DFT | Amber | 2015-04-01 | 2027-04-30 | 17.94 | 15.74 | -11.00% | 0.00 |
| A417 Air Balloon | 2023 | DFT | Green | 2015-04-01 | 2027-08-31 | 33.40 | 30.50 | -9.00% | 482.00 |
| A428 Black Cat to Caxton Gibbet | 2019 | DFT | Amber/Green | 2015-04-01 | 2025-04-01 | 14.30 | 8.30 | -42.00% | 809.80 |
| A428 Black Cat to Caxton Gibbet | 2020 | DFT | Amber/Green | 2015-04-01 | 2025-04-01 | 11.02 | 19.30 | 0.75% | 809.98 |
| A428 Black Cat to Caxton Gibbet | 2021 | DFT | Amber/Green | 2015-04-01 | 2025-04-01 | 25.00 | 25.00 | 0.00% | 812.50 |
| A428 Black Cat to Caxton Gibbet | 2022 | DFT | Amber | 2015-04-01 | 2027-09-09 | 48.30 | 28.10 | -42.00% | 0.00 |
| A428 Black Cat to Caxton Gibbet | 2023 | DFT | Amber | 2015-04-01 | None | 60.00 | 34.40 | -43.00% | 0.00 |
| A66 Northern Trans-Pennine | 2021 | DFT | Green | 2017-07-05 | 2030-03-31 | 13.72 | 13.72 | 0.00% | 1,289.40 |
| A66 Northern Trans-Pennine | 2022 | DFT | Amber | 2017-07-05 | 2030-03-31 | 27.17 | 42.30 | 56.00% | 1,140.00 |
| A66 Northern Trans-Pennine | 2023 | DFT | Amber | 2017-07-05 | 2030-03-31 | 68.80 | 66.76 | -3.00% | 0.00 |
| ABUJA New Office and Residence | 2013 | FCO | Amber | 2010-12-01 | 2017-12-01 | 0.95 | 0.95 | 0.00% | 39.00 |
| ABUJA New Office and Residence | 2014 | FCO | Amber | 2011-01-01 | 2017-12-01 | 0.66 | 0.66 | 0.00% | 39.00 |
| ABUJA New Office and Residence | 2015 | FCO | Amber/Green | 2011-01-01 | 2017-12-01 | 19.89 | 19.89 | 0.00% | 46.00 |
| ABUJA New Office and Residence | 2016 | FCO | Amber | 2011-01-01 | 2016-12-01 | 18.80 | 18.80 | 0.0% | 46.00 |
| ABUJA New Office and Residence | 2017 | FCO | Amber | 2011-01-01 | 2017-12-01 | 13.40 | 13.70 | 2.00% | 46.00 |
| Accelerated Houseblocks | 2022 | MOJ | Amber | 2020-09-28 | 2024-05-13 | 52.20 | 18.59 | -64.00% | 12,208.00 |
| Accelerated Houseblocks | 2023 | MOJ | Amber | 2020-09-28 | None | 357.00 | 61.50 | -83.00% | 0.00 |
| ADMS | 2017 | DWP | Amber | 2016-03-01 | 2017-03-31 | 168.62 | 168.62 | 0.00% | 602.86 |
| Affordable Homes Programme | 2023 | DLUHC | Amber | 2021-01-03 | 2029-04-30 | 1,895.17 | 1,114.36 | -41.00% | 11,583.00 |
| AI Labs | 2022 | DHSC | Red | 2020-07-01 | 2024-03-31 | 60.90 | 51.00 | -16.00% | 188.00 |
| AI Labs | 2023 | DHSC | Amber | 2020-07-01 | 2024-03-31 | 38.03 | 38.03 | 0.00% | 160.00 |
| Airport Capacity Programme | 2017 | DFT | Amber | 2015-07-01 | 2029-12-31 | 14.00 | 9.00 | -36.00% | 79.00 |
| Airport Capacity Programme | 2018 | DFT | Amber | 2015-07-01 | 2029-12-31 | 14.70 | 8.80 | -40.00% | 22,747.00 |
| Airseeker | 2013 | MOD | Amber/Green | 2010-03-18 | 2018-04-01 | 110.49 | 128.88 | 16.64% | 1,271.12 |
| Airseeker | 2014 | MOD | Amber | 2010-03-18 | 2018-04-01 | 141.57 | 150.19 | 6.09% | 1,219.40 |
| Airseeker | 2015 | MOD | Amber/Green | 2010-03-18 | 2018-04-01 | 132.22 | 127.96 | -3.20% | 753.11 |
| Airseeker | 2016 | MOD | Amber/Green | 2010-03-18 | 2018-04-01 | 134.59 | 132.06 | 0.0% | 757.80 |
| Airseeker | 2017 | MOD | Amber/Green | 2010-03-18 | 2018-04-01 | 91.41 | 102.98 | 13.00% | 759.84 |
| Apprenticeships Reform Programme | 2017 | DFE | Amber/Red | 2015-05-08 | 2021-04-01 | 1,919.40 | 1,784.20 | -7.00% | 11,347.50 |
| Apprenticeships Reform Programme | 2018 | DFE | Amber | 2015-05-08 | 2021-04-01 | 2,036.10 | 1,684.10 | -17.00% | 11,347.50 |
| Apprenticeships Reform Programme | 2019 | DFE | Amber | 2015-05-08 | 2021-04-01 | 2,243.30 | 1,863.60 | -17.00% | 11,347.50 |
| Apprenticeships Reform Programme | 2020 | DFE | Amber/Red | 2015-05-08 | 2021-04-01 | 2,470.01 | 2,183.00 | -0.12% | 11,347.41 |
| Apprenticeships Reform Programme | 2021 | DFE | Green | 2015-05-08 | 2021-04-01 | 2,675.20 | 1,899.48 | -29.00% | 11,347.50 |
| Approved Premises | 2021 | MOJ | Amber | 2019-04-01 | 2024-03-31 | 7.91 | 4.07 | -49.00% | 57.79 |
| Approved Premises | 2022 | MOJ | Green | 2019-04-01 | 2024-03-31 | 14.28 | 8.90 | -38.00% | 65.00 |
| Approved Premises Expansion | 2023 | MOJ | Green | 2019-04-01 | 2023-07-30 | 13.73 | 13.77 | 0.00% | 80.00 |
| Armed Forces People Programme | 2018 | MOD | Amber/Red | 2015-11-25 | 2021-03-31 | 11.10 | 24.56 | 121.00% | 57.38 |
| Armed Forces People Programme | 2019 | MOD | Amber/Red | 2015-11-25 | 2021-03-31 | 27.27 | 22.53 | -17.00% | 69.65 |
| Armed Forces Recruitment Programme | 2020 | MOD | Amber/Red | 2018-03-15 | 2023-02-01 | 5.10 | 5.10 | 0.0% | 1,730.24 |
| Armed Forces Recruitment Programme | 2021 | MOD | Amber | 2018-03-15 | 2024-09-30 | 7.36 | 7.82 | 6.00% | 0.00 |
| Armed Forces Recruitment Programme | 2022 | MOD | Amber | 2018-03-15 | 2024-09-30 | 0.00 | 0.00 | 0.00% | 0.00 |
| Armed Forces Recruitment Programme | 2023 | MOD | Amber | 2018-03-15 | 2024-09-30 | 0.00 | 0.00 | 0.00% | 0.00 |
| Armour Main Battle Tank | 2017 | MOD | Amber | 2014-12-04 | 2026-06-01 | 6.37 | 5.57 | -13.00% | 744.79 |
| Armour Main Battle Tank | 2018 | MOD | Amber | 2014-12-04 | 2026-06-01 | 26.51 | 26.02 | -2.00% | 0.0 |
| Armour Main Battle Tank | 2019 | MOD | Amber | 2014-12-04 | 2026-06-01 | 0.0 | 0.0 | 0.0% | 0.0 |
| Armour Main Battle Tank | 2020 | MOD | Amber | 2014-12-04 | 2028-07-31 | 12.46 | 11.95 | -0.04% | 1,304.19 |
| Armour Main Battle Tank | 2021 | MOD | Amber | 2017-12-18 | 2026-06-01 | 9.40 | 9.10 | -3.00% | 1,399.17 |
| Armour MBT 2025 | 2022 | MOD | Amber | 2014-12-04 | 2026-06-01 | 65.55 | 76.20 | 16.00% | 1,372.00 |
| Armour MBT 2025 | 2023 | MOD | Amber | 2014-12-04 | 2031-05-22 | 107.86 | 87.87 | -19.00% | 1,435.00 |
| Armoured Cavalry 2025 | 2016 | MOD | Amber | 2014-01-22 | 2025-04-30 | 245.92 | 237.06 | 0.0% | 6,831.53 |
| Armoured Cavalry 2025 | 2017 | MOD | Amber | 2014-12-04 | 2025-04-30 | 317.43 | 309.07 | -3.00% | 6,248.64 |
| Armoured Cavalry 2025 | 2018 | MOD | Amber | 2014-01-22 | 2025-04-30 | 512.00 | 491.41 | -4.00% | 6,258.19 |
| Armoured Cavalry 2025 | 2019 | MOD | Amber | 2014-01-22 | 2025-04-30 | 627.86 | 542.50 | -14.00% | 6,291.94 |
Click on the Project name for annual report details for that year. Basic search box only accepts a single word - click in box to get drop down search for more complex queries.