Reports for project: Transpennine Route Upgrade

Reports: Year Organisation DCA status     Start date     End date Base £m Fcast £m Variance% WLCost £m   Category
Details 2021 2021 DFT Amber 2017-07-01 2028-07-31 253.0 239.0 -6.0 3,506.0   Infrastructure
Details 2022 2022 DFT Amber 2017-07-01 2041-10-17 450.0 412.0 -8.0 9,185.0   Infrastructure
Details 2023 2023 DFT Amber 2017-07-01 2041-10-17 661.5 590.0 -11.0 11,453.0   Infrastructure

 3 reports. Select Details to see the full report for that year. Select Year/Org/Category to see all reports for that heading.