Reports for project: Mobile Infrastructure Project
Reports: | Year | Organisation | DCA status     | Start date     | End date | Base £m | Fcast £m | Variance% | WLCost £m |   Category |
---|---|---|---|---|---|---|---|---|---|---|
Details 2013 | 2013 | DCMS | Amber | 2011-10-03 | 2015-03-31 | 12.5 | 4.5 | -64.0 | 154.5 |   Infrastructure |
Details 2014 | 2014 | DCMS | Amber/Green | 2011-10-01 | 2015-03-31 | 71.0 | 14.0 | -80.3 | 155.0 |   Infrastructure |
Details 2015 | 2015 | DCMS | Amber/Red | 2011-10-01 | 2016-03-31 | 71.5 | 25.6 | -64.2 | 157.1 |   Infrastructure |
Details 2016 | 2016 | DCMS | Amber | 2011-10-01 | 2016-03-31 | 28.5 | 28.1 | None | 44.0 |   Infrastructure |
4 reports. Select Details to see the full report for that year. Select Year/Org/Category to see all reports for that heading.
Google Search on project title - opens in new window
Manual Contracts Search - opens in new window
Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories
Acknowledgement: GMPP data has been re-used under the Open Government Licence. Related links do not imply any endorsement.