Reports for project: Glen Parva New Build Prison
Reports: | Year | Organisation | DCA status     | Start date     | End date | Base £m | Fcast £m | Variance% | WLCost £m |   Category |
---|---|---|---|---|---|---|---|---|---|---|
Details 2020 | 2020 | MOJ | Amber | 2019-01-31 | 2023-11-05 | 16.0 | 9.9 | -0.4 | 6,104.8 |   Infrastructure |
Details 2021 | 2021 | MOJ | Amber/Green | 2019-01-31 | 2023-11-05 | 91.4 | 85.3 | -7.0 | 6,775.7 |   Infrastructure |
Details 2022 | 2022 | MOJ | Amber | 2019-01-31 | 2023-11-05 | 195.2 | 178.8 | -8.0 | 6,765.0 |   Infrastructure |
Details 2023 | 2023 | MOJ | Amber | 2019-01-31 | 2023-11-05 | 92.1 | 89.0 | -3.0 | 6,753.0 |   Infrastructure |
4 reports. Select Details to see the full report for that year. Select Year/Org/Category to see all reports for that heading.
Google Search on project title - opens in new window
Manual Contracts Search - opens in new window
Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories
Acknowledgement: GMPP data has been re-used under the Open Government Licence. Related links do not imply any endorsement.