Reports for project: Further Electrification of Midland Main Line (MML3)
Reports: | Year | Organisation | DCA status     | Start date     | End date | Base £m | Fcast £m | Variance% | WLCost £m |   Category |
---|---|---|---|---|---|---|---|---|---|---|
Details 2022 | 2022 | DFT | Amber | 2022-01-21 | 2030-12-31 | 24.0 | 24.0 | 0.0 | 1,468.0 |   Infrastructure |
Details 2023 | 2023 | DFT | Amber | 2022-01-21 | 2030-12-31 | 67.0 | 14.0 | -79.0 | 1,468.0 |   Infrastructure |
2 reports. Select Details to see the full report for that year. Select Year/Org/Category to see all reports for that heading.