2023 Report details for project: 10k Additional Prison Places - New Build
| Project name | 10k Additional Prison Places - New Build - there is only one report for this project |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | MOJ (D18) - see all reports for this organisation |
| Report year | 2023 (data is from September 2022) |
| Category | Infrastructure - see all reports for this category |
| Description: | The New Build project supports our 20,000 additional prison places commitment; its scope is to build four new prisons. |
| DCA (RAG) | Amber |
| DCA text: | Compared to financial year 21/22-Q4, the IPA's DCA rating at 22/23-Q4 remained at Amber. This is primarily due to the following factors.Compared to21/22 Q4, theproject'sDCA rating remained Amber.The Amber assessment is due to planning permission refusals atthree of the new prison sites which are subject to planning appeals.There has been positive progress building the third of our new prisons (Full Sutton).(The main works contract was executed on 21 July 2022 following which construction commenced in August 2022 and delivery is on track). |
| Start date | 2020-03-02 |
| End date | None |
| Schedule text | Exempt under Section 43 of the FOI Act 2000 (Commercial Interests) - Commercial interests. |
| Baseline | £230.27m |
| Forecast | £221.00m |
| Variance | -4.00% |
| Variance text: | Variance less than 5% so no narrative required |
| Whole Life Cost | £0.00m |
| WLCost text: | Exempt under Section 43 of the FOI Act 2000 (Commercial Interests) - Commercial interests. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2023.csv |