2023 Report details for project: CHINOOK CAPABILITY SUSTAINMENT PROGRAMME (CSP)

Project name CHINOOK CAPABILITY SUSTAINMENT PROGRAMME (CSP) - there are 2 reports for this project: 2022, 2023
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation MOD (D17 ) - see all reports for this organisation
Report year 2023 (data is from September 2022)
Category Military - see all reports for this category
Description: Chinook Capability Sustainment Programme Tranche 1 will provide a modern and cost effective transformational change to the UK Special User's vertical heavy lift capability with the procurement of 14 new-build Chinook aircraft. The aircraft will be able to operate and survive in a multitude of environments, conducting high-tempo missions with minimal logistics footprint and high-levels of interoperability with key allies, to beyond 2050.
DCA (RAG) Amber
DCA text: Compared to financial year 21/22-Q4, the DCA rating at 22/23-Q4 decreased from Green (IPA rating) to Amber (SRO rating). This is primarily due to the following factors. Inflationary pressures and supply chain delays will increase affordability risk and programme success relies heavily on the release of capability information from the US to the UK. The Programme is currently working through rescheduling activities with the US Department of Defence which will culminate in a revised schedule and financial profile. The lack of key skills and experience, though mitigated by the arrival of a new Programme Director, Programme Manager and five Programme Control contractors, remains a risk given the high degree of churn.
Start date 2017-03-31
End date 2030-12-31
Schedule text Compared to financial year 21/22-Q4, the project's end-date at 22/23-Q4 remained schedule to finish on 2030-12-31. This is primarily due to the following factors.NA
Baseline £85.35m
Forecast £56.51m
Variance -34.00%
Variance text: The budget variance exceeds 5%. This is primarily due to the following factors: The Programme has not been able to commit funds at the rate anticipated as a consequence of US Government's delay in placing contracts due to resourcing challenges.
Whole Life Cost £1,602.00m
WLCost text: Compared to financial year 21/22-Q4, the project's departmental-agree Whole Life Cost at 22/23-Q4 increased from 1519m. to 1602m. This is primarily due to the following factors. The cost growth due to a net 18 month deferral. The programme will re-baseline when the full implications are confirmed.
Notes1:
Notes2:
Sourcefile IPA_2023.csv