2023 Report details for project: A66 Northern Trans-Pennine

Project name A66 Northern Trans-Pennine - there are 3 reports for this project: 2021, 2022, 2023
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation DFT (D9) - see all reports for this organisation
Report year 2023 (data is from September 2022)
Category Infrastructure - see all reports for this category
Description: Dualling of the remaining single-carriageway sections on the A66 between M6 J40 Penrith and A1M Scotch Corner, creating a continuous dual carriageway across the Pennines.
DCA (RAG) Amber
DCA text: Compared to financial year 21/22-Q4, the DCA rating at 22/23-Q4 remained at Amber (SRO rating). This is primarily due to the following factors.An Action Plan has been put in place to address the five actions from the last Assurance Review, and progress is monitored on a monthly basis. The next the IPA Assurance Review (scheduled for July 2023) will formally review progress against the Action Plan.
Start date 2017-07-05
End date 2030-03-31
Schedule text Compared to financial year 21/22-Q4, the project's end-date at 22/23-Q4 remained schedule to finish on 2030-03-31. This is primarily due to the following factors.Compared to financial year 21/22-Q4, the project's end-date at 22/23-Q4 remained schedule to finish on 2030-03-31. This is primarily due to the following factors. The committed milestones of Start of Work in Q4 23/24 and Open for Traffic in Road Investment Period 3 are still on track. Over the course of Financial Year 22/23, the project has achieved a number of important milestones, including Development Consent Order Submission (June 2022), National Highways Project Controls Framework Stage 3 completion (June 2022), contract award with the Delivery Integration Partners (October 2022), and the commencement of the Development Consent Order Examination in November 2022.
Baseline £68.80m
Forecast £66.76m
Variance -3.00%
Variance text: Exempt under Section 43 of the FOI Act 2000 (Commercial Interests) - Commercial interests.
Whole Life Cost £0.00m
WLCost text: Exempt under Section 43 of the FOI Act 2000 (Commercial Interests) - Commercial interests.
Notes1:
Notes2:
Sourcefile IPA_2023.csv