2023 Report details for project: A428 Black Cat to Caxton Gibbet

Project name A428 Black Cat to Caxton Gibbet - there are 5 reports for this project: 2019, 2020, 2021, 2022, 2023
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation DFT (D9) - see all reports for this organisation
Report year 2023 (data is from September 2022)
Category Infrastructure - see all reports for this category
Description: The scheme provides a new off-line two lane dual carriageway between Black Cat roundabout on the A1 in Bedfordshire and Caxton Gibbet roundabout on the A428 in Cambridgeshire.
DCA (RAG) Amber
DCA text: Compared to financial year 21/22-Q4, the Senior Responsible Owner's DCA rating at 22/23-Q4 remained at Amber. This is primarily due to the following factors.The A428 Black Cat to Caxton Gibbet Project is currently in the development phase. The Development Consent Order (DCO) process has concluded with Secretary of States (SoS) granting consent for the scheme August 2022. There have been delays to the schemes delivery plan milestones due to a Judicial Review challenge. The impact of delays associated with the legal process has significantly impacted the projects programme and cost. The project will be returning through governance beginning in Q2 2023/2024 for approval of an updated Full Business Case and re-baseline.
Start date 2015-04-01
End date None
Schedule text There have been delays to the schemes delivery plan milestones due to a Judicial Review challenge. The impact of delays associated with the legal process has significantly impacted the projects programme. The project will be returning through governance with a full impact analysis of delay and re-baseline, ahead of Start of Works.
Baseline £60.00m
Forecast £34.40m
Variance -43.00%
Variance text: There have been delays to the schemes delivery plan milestones due to a Judicial Review challenge. The impact of delays associated with the legal process has significantly impacted the projects programme and cost. The scheme missed the planned Start of Works milestone for December 2022, which has decreased the in year costs reflecting the reduced activity necessitated by the legal challenge.
Whole Life Cost £0.00m
WLCost text: Exempt under Section 43 of the FOI Act 2000 (Commercial Interests) - Commercial interests.
Notes1:
Notes2:
Sourcefile IPA_2023.csv