2023 Report details for project: 2nd Generation UK Search and Rescue Aviation

Project name 2nd Generation UK Search and Rescue Aviation - there are 2 reports for this project: 2022, 2023
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation DFT (D9) - see all reports for this organisation
Report year 2023 (data is from September 2022)
Category Transformation - see all reports for this category
Description: The UK Search and Rescue Second Generation (UKSAR2G) programmes is the UK's replacement aviation Search and Rescue (SAR) and Aerial Surveillance and Verification (ASV) services that will continue to save lives, protect the UK's economic interests and maintain aeronautical compliance with International Conventions beyond 2024.
DCA (RAG) Green
DCA text: Compared to financial year 21/22-Q4, the Senior Responsible Owner's DCA rating at 22/23-Q4 remained at Green. This is primarily due to the following factors.The tender assessment was completed and the contract awarded to Bristow Helicopters Ltd. The programme is mobilising and regular meetings have been established between the MCA and BHL. Internal workstreams are being established to manage the transition between the old and the new contracts.The Gateway Review found that the Programme is well-established and constructed and seeks to deliver a vital emergency service without loss of continuity.
Start date 2019-12-16
End date 2026-12-31
Schedule text Compared to financial year 21/22-Q4, the project's end-date at 22/23-Q4 remained schedule to finish on 2026-12-31. This is primarily due to the following factors.Compared to financial year 21/22-Q4, the project's end-date at 22/23-Q4 remained schedule to finish on 2026-12-31. This is primarily due to the following factors. The contract has been awarded and the FBC approved. The contracted schedule maintains the projected end date.
Baseline £0.00m
Forecast £0.00m
Variance None%
Variance text: The GMPP project did not provide data
Whole Life Cost £1,959.00m
WLCost text: Compared to financial year 21/22-Q4, the project's departmental-agree Whole Life Cost at 22/23-Q4 decreased from 2607m. to 1959m. This is primarily due to the following factors.Compared to financial year 21/22-Q4, the project's departmental-agree Whole Life Cost at 22/23-Q4 decreased from 2607m. to 1959m. This is primarily due to the following factors. The cost of the accepted bid was lower than anticipated and this has been reflected in the Full Business Case which has been approved by DfT and HMT. Milestone payments will be made as each base transitions to service.
Notes1:
Notes2:
Sourcefile IPA_2023.csv

Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories