2022 Report details for project: Building Safety Programme - ACM Remediation

Project name Building Safety Programme - ACM Remediation - there are 2 reports for this project: 2021, 2022
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation DLUHC (D4) - see all reports for this organisation
Report year 2022 (data is from September 2021)
Category Infrastructure - see all reports for this category
Description: This programme was established to ensure the removal of unsafe aluminium composite material (ACM) cladding from all high-rise residential buildings in England, including all public and private sector buildings, student accommodation and hotels.
DCA (RAG) Green
DCA text: Compared to financial year 2020/21-Q4, the IPA's DCA rating at 2021/22-Q4 decreased from Amber/Green to Green. The ACM programme has continued to progress well and manage the pipeline of buildings through the processes required to complete remediation works. The programme team is aligned to the Infrastructure Projects Authority's delivery confidence rating and continues to focus on the need to quantify the impact to delivery of the complex buildings that remain.
Start date 2017-06-15
End date 2022-06-30
Schedule text The revised end date will be built in as the programme evaluates its objectives and dates. Despite the increase in buildings within scope, the majority of buildings will have completed remediation by 2023-Q4, with the project end date estimated as 2024-Q4.
Baseline £141.70m
Forecast £124.38m
Variance -12.00%
Variance text: The budget variance exceeds 5%. The variance of 2021/22 outturn against budget largely relates buildings in scope increasing from the original number of 428 to 486
Whole Life Cost £634.00m
WLCost text: Compared to 2021-Q4, the programme's Baseline Whole Life Cost increased from £589m to £634m. This is due to a steady stream of new buildings coming into scope of the fund, several buildings initially considered out of scope have since had ACM cladding identified, alongside the average remediation cost being higher than initially forecast because of additional qualifying work needed after start on site and the increasing impact of inflationary pressures.
Notes1:
Notes2:
Sourcefile IPA_2022.csv