2022 Report details for project: Astute Boats 1-7
| Project name | Astute Boats 1-7 - there are 11 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022, 2023 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | MOD (D17 ) - see all reports for this organisation |
| Report year | 2022 (data is from September 2021) |
| Category | Military - see all reports for this category |
| Description: | To deliver the seven Boat Astute Class within approved performance, cost and time parameters, while actively contributing to the sustainment of the UK submarine design and manufacturing capability. |
| DCA (RAG) | Amber |
| DCA text: | Compared to financial year 20/21-Q4, the IPA's DCA rating increased from Amber/Red to Amber. This is primarily due to the following factors: The removal of the incremental Amber/Red and Amber/Green rating. Despite continued COVID-19 challenges, the Astute build programme has achieved its major build and commissioning milestones though this financial year, and therefore delivery confidence of Amber is maintained. HMS AUDACIOUS commissioned, HMS ANSON is afloat, HMS AGEMEMNON and HMS AGINCOURT are being fitted out. However, the programme still carries schedule risk because of workload demands and access to the limited number of Suitably Qualified and Experienced Personnel that is not limited to Defence but also Industry and the wider Nuclear Sector. |
| Start date | 1997-03-17 |
| End date | None |
| Schedule text | Exempt under Section 24 of the FOI Act 2000 (National security) |
| Baseline | £371.56m |
| Forecast | £386.07m |
| Variance | 4.00% |
| Variance text: | The budget variance is inferior or equal to 5% |
| Whole Life Cost | £10,833.00m |
| WLCost text: | Compared to 2021-Q4 the project's Baseline Whole Life Cost increased from 10830.05 (£m) to 10832.67 (£m) This is primarily due to the following factors: Impacts on the submarine build schedules including those caused by Covid-19. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2022.csv |