2022 Report details for project: Approved Premises

Project name Approved Premises - there are 2 reports for this project: 2021, 2022
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation MOJ (D18) - see all reports for this organisation
Report year 2022 (data is from September 2021)
Category Transformation - see all reports for this category
Description: The Approved Premises Expansion Programme (APEX) will increase capacity in Approved Premises. Approved Premises are residential units in the community which house and monitor offenders following their release from prison. They protect the public and rehabilitate offenders. APEX was initiated in response to the ministerial commitment made on 24th January 2019 to build over 200 additional places in Approved Premises to meet increased demand
DCA (RAG) Green
DCA text: Compared to financial year 20/21-Q4, the DCA rating at 21/22-Q4 decreased from Amber to Green The programme has surpassed its milestoneto deliver 100 beds by March 2022. A further 67 bed spaces are currently in delivery. There is confidence that the identified opportunities can deliver the overall 200+ increase before the target end date
Start date 2019-04-01
End date 2024-03-31
Schedule text Compared to 2021-Q4, your project end-date remained scheduled to finish on 31 MAR 2024 This is primarily due to the following factors: The project is on track to meet the March 2024 target and has achieved the interim milestone for 100 additional bed spaces by March 2022.
Baseline £14.28m
Forecast £8.90m
Variance -38.00%
Variance text: The budget variance exceeds 5%. The Programme underspent by £5.5m in 2021-22. This is primarily due to: two key factors firstly, delays to planning permission and secondly, delays caused by the COVID-19 pandemic.
Whole Life Cost £65.00m
WLCost text: Compared to2021-Q4, the projects Baseline Whole Life Cost increased from 57.79 (£m) to 65.15 (£m). This is primarily due to the following factors: The project entering into new contracts for Approved Premises Service with increased staff and facilities management costs.
Notes1:
Notes2:
Sourcefile IPA_2022.csv