2022 Report details for project: A400M
| Project name | A400M - there are 11 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022, 2023 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | MOD (D17 ) - see all reports for this organisation |
| Report year | 2022 (data is from September 2021) |
| Category | Military - see all reports for this category |
| Description: | The A400M Programme is intended to deliver and support ATLAS aircraft into service which are capable of: - Operating in domestic and international air environments, including contested air, to well-found and remote bases and airstrips. - The inter- and intra-theatre deployment, sustainment and recovery of passengers and freight. - Providing an aerial delivery capability in order to airdrop personnel and freight to the point of need. - Providing inter- and intra-theatre aeromedical movement of casualties. - Providing fixed-wing support to Standing Home Commitments and Contingent Overseas Operations, consistent with Defence Commitments' direction in support of specialist users. |
| DCA (RAG) | Amber |
| DCA text: | Compared to financial year 20/21-Q4, the IPA's DCA rating remained at Amber. This is primarily due to the following factors: The programme continues to make good progress with key capabilities now graduated for Front Line training and operations. There remains risk as expected in this type of programme and some adjustment of the schedule in response to aircraft availability may be needed to ensure timely delivery within expected timescales |
| Start date | 2000-05-17 |
| End date | 2024-03-31 |
| Schedule text | Compared to 2021-Q4, the project end-date remained scheduled to finish on 31 March 2024. |
| Baseline | £214.19m |
| Forecast | £153.67m |
| Variance | -28.00% |
| Variance text: | The budget variance exceeds 5%. This predicted underspend is because of prudent savings measures taken against the programme and through reprofiling to delivery. |
| Whole Life Cost | £3,802.00m |
| WLCost text: | Compared to 2021-Q4, the projects Baseline Whole Life Cost has increased by £18.513M (£3783.029M at Q4 20/21 and £3801.542M at Q4 21/22). This is primarily due to the following factors: Fluctuations in foreign exchange rates that have been offset in part by saving measures and reprofiling through to delivery. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2022.csv |