2022 Report details for project: 5G Testbeds and Trials
| Project name | 5G Testbeds and Trials - there are 4 reports for this project: 2019, 2020, 2021, 2022 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | DCMS (D5 ) - see all reports for this organisation |
| Report year | 2022 (data is from September 2021) |
| Category | Infrastructure - see all reports for this category |
| Description: | The 5G Testbeds and Trials Programme is the Government's nationally coordinated programme of investment in 5G. The Programme looks to harness areas where the UK has a competitive advantage - such as scientific research, engineering talent and our rich variety of technology businesses. The Programme is exploring the benefits and challenges of deploying 5G technologies. |
| DCA (RAG) | Green |
| DCA text: | Compared to financial year 20/21-Q4, the DCA rating at 21/22-Q4 decreased from Amber/Green to Green The Programme was reviewed by the IPA in February 2021, and received an overall RAG delivery confidence assessment of 'Amber'. Since then, the Programme team has worked on the recommendations made in that report, which have either now been completed or have been progress. The Programme was granted permission in the Autumn Spending Review in 2021 to reprofile into the next financial year (2022/23). The Programme was due to close all projects on 31 March 2022; 12 projects have been extended for a range of 3 - 9 months to allow for more full benefits realisation. The remaining projects are preparing for closure, with the Programme team working closely with project partners and internal colleagues to manage this in a controlled manner. Numerous showcases and events have been held between January 2022 - end of March 2022 across the projects, with positive media reporting taking place around these. The likelihood of any significant new risks which materially damage the Programme as a whole is very low. |
| Start date | 2017-02-28 |
| End date | 2023-03-31 |
| Schedule text | Compared to 2021-Q4, your project end-date increased from 31 MAR 2022 to 31 MAR 2023 This is primarily due to the following factors: The Programme was granted permission in the Autumn Spending Review in 2021 into the next financial year (2022/23). The majority of the projects in the Programme will still close on 31 March 2022, with a smaller number (12) extended for a short period of 3-9 months on a case-by-case basis. The reprofile, as well as allowing for these short extensions, will also see the Programme team remain in place to carry out closure activities and conclude the Programme in a controlled manner. The date is therefore aligned with the end of the next financial year (although all activity and final reviews are expected to be completed prior to this date). |
| Baseline | £44.94m |
| Forecast | £44.62m |
| Variance | -1.00% |
| Variance text: | The budget variance is inferior or equal to 5%. |
| Whole Life Cost | £227.00m |
| WLCost text: | Compared to 2021-Q4, the projects Baseline Whole Life Cost decreased from 232.75 (£m) to 227.09 (£m). This is primarily due to the following factors: To date, the programme has spent combined RES-del and CAP-del £156.6m |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2022.csv |