2022 Report details for project: 10,000 Additional Prison Places Programme - Estate Expansions

Project name 10,000 Additional Prison Places Programme - Estate Expansions - there are 2 reports for this project: 2021, 2022
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation MOJ (D18) - see all reports for this organisation
Report year 2022 (data is from September 2021)
Category Infrastructure - see all reports for this category
Description: The prison population is forecast to rise significantly during the 2020s, and the department is bringing forward new prison places to accommodate new offenders. In August 2019 the Prime Minister announced £2.5bn of funding to deliver 10,000 additional prison places through the building of new prisons and expanding the prison estate. This has since been amended to £3.8bn and Estate Expansions now forms part of the 20,000 Additional Prison Places commitment; its scope is to deliver places through expanding the existing estate by building new houseblocks on existing prison sites, modular Category D units for the Open Prison estate, major refurbishments, increased spaces in the Women's estate and a number of smaller scale investments.
DCA (RAG) Amber
DCA text: Compared to financial year 20/21-Q4, the IPA's DCA rating at 21/22-Q4 remained at Amber Progress has been made on critical activity; Category D Expansion Project Full Business Case has been approved and critical path Local Planning Applications (LPA) for the Houseblocks and Refurbishments project have been approved. Confidence continues to be affected by the impact of COVID-19 and EU Exit, planning permission delays, inflationary cost pressures and supply chain impacts.
Start date 2020-03-02
End date 2025-05-01
Schedule text Compared to 20/21 Q4,the project end date has remained static.
Baseline £272.27m
Forecast £129.49m
Variance -52.00%
Variance text: The budget variance exceeds 5%. The budget is based primarily on estimates provided for several separate projects which at that time were at an early stage of their development and will be refined further in the full business cases.
Whole Life Cost £8,333.00m
WLCost text: Compared to2021-Q4, the projects Baseline Whole Life Cost increased from 8003.04 (£m) to 8333.01 (£m). This is primarily due to the following factors: Construction market inflation; and constrained ability to undertake site surveys during the COVID-19 Pandemic.
Notes1:
Notes2:
Sourcefile IPA_2022.csv

Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories


Acknowledgement: GMPP data has been re-used under the Open Government Licence.