2021 Report details for project: Workplace Services Transformation Programme
Project name | Workplace Services Transformation Programme - there are 3 reports for this project: 2021, 2022, 2023 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | CO (D2 ) - see all reports for this organisation |
Report year | 2021 (data is from March 2021) |
Category | Transformation - see all reports for this category |
Description: | The Workplace Services Transformation Programme (WSTP) has been established to realise the ambition of a transformed workplace experience for all GPA customers (end users) and to ensure better value for our clients (Departments). |
DCA (RAG) | Amber/Red |
DCA text: | The Infrastructure Project Authority's Delivery Confidence Assessment rating is Amber/red.This is primarily due to the following factors: The WST Programme funding has been secured through the SR20 bid 21/22 (and will be subject to a SR21 bid for ongoing funding). The WSTP Supply Chain Project (SCP), Outline Business Case (OBC) seeking authority to go to market for new FM Contracts was endorsed by the GPA Investment Committee and approval has been requested from the GPA Board on 8th April 2021. |
Start date | 2020-05-01 |
End date | 2023-09-01 |
Schedule text | The project end-date is 01 September 2023. This is primarily due to the following factors: Project has not yet been baselined. Outline Business Case (OBC) seeking authority to go to market for new FM Contracts was endorsed by the GPA Investment Committee and approval has been requested from the GPA Board. |
Baseline | £0.00m |
Forecast | £187.63m |
Variance | 0.00% |
Variance text: | Project has not yet been baselined. One off spend incurred was for development of OBC, recurring old costs are Facilities Management costs in line with current contract spend |
Whole Life Cost | £0.00m |
WLCost text: | Project has not yet been baselined. One off spend incurred was for development of OBC, recurring old costs are Facilities Management costs in line with current contract spend |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2021.csv |