2021 Report details for project: Glen Parva New Build Prison

Project name Glen Parva New Build Prison - there are 4 reports for this project: 2020, 2021, 2022, 2023
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation MOJ (D18) - see all reports for this organisation
Report year 2021 (data is from March 2021)
Category Infrastructure - see all reports for this category
Description: The prison population is forecast to rise significantly during the 2020s and the department is bringing forward new prison places to accommodate new offenders. The new prison at Glen Parva will be a resettlement prison, creating 1680 Category C resettlement places. The operation of the prison is subject to a competition via a call-off from the Prison Operator Services Framework.
DCA (RAG) Amber/Green
DCA text: Compared to financial year 19/20-Q2, the Infrastructure Project Authority's Delivery Confidence Assessment rating decreased from Amber to Amber/Green. This is primarily due to the following factors: The construction of the prison and the commercial process to select the prison operator are both on track.
Start date 2019-01-31
End date 2023-11-05
Schedule text Compared to financial year 19/20-Q2, the project's end-date remained scheduled to finish on 05 November 2023 This is primarily due to the following factors: The project remains on track to complete by November 2023.
Baseline £91.42m
Forecast £85.32m
Variance -7.00%
Variance text: The budget variance exceeds 5%. Forecast capital expenditure in the current FY has reduced due to changes to programme made by the main contractor, adverse weather conditions and some labour shortages
Whole Life Cost £6,775.73m
WLCost text: Compared to financial year 19/20-Q2, the projects Baseline Whole Life Cost increased from £6104.77m to £6775.73m. This is primarily due to the following factors: The initial cost estimates were refined and updated in the full business case that was approved in July 2020
Notes1:
Notes2:
Sourcefile IPA_2021.csv