2021 Report details for project: Nuclear Warhead Capability Sustainment Programme
Project name | Nuclear Warhead Capability Sustainment Programme - there are 9 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | MOD (D17 ) - see all reports for this organisation |
Report year | 2021 (data is from March 2021) |
Category | Military - see all reports for this category |
Description: | To deliver and sustain the capability (skills, technology, science, personnel, production and support) to underwrite the UK nuclear warhead stockpile now and in the future. |
DCA (RAG) | Exempt FOI |
DCA text: | Exempt under Section 24 of the Freedom of Information Act 2000 (National security) |
Start date | 2008-04-01 |
End date | 2025-04-30 |
Schedule text | Compared to financial year 19/20-Q2, the project's end-date remained scheduled to finish on 30 April 2025 This is primarily due to the following factors: |
Baseline | £1,134.23m |
Forecast | £1,077.91m |
Variance | -5.00% |
Variance text: | The budget variance is less than or equal to 5%. |
Whole Life Cost | £19,984.43m |
WLCost text: | Exempt under Section 27 of the Freedom of Information Act 2000 (International relations) |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2021.csv |
Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories
Acknowledgement: GMPP data has been re-used under the Open Government Licence.