2021 Report details for project: Next Generation Communications Network
Project name | Next Generation Communications Network - there are 3 reports for this project: 2021, 2022, 2023 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | MOD (D17 ) - see all reports for this organisation |
Report year | 2021 (data is from March 2021) |
Category | ICT - see all reports for this category |
Description: | The Next Generation Communications Network programme is responsible for delivering the Ministry of Defences's future network in support of the Digital Backbone as well as ensuring that the Ministry of Defences's fixed network continues to function to agreed standards of resilience and performance during the bridging period until the Programme delivers its replacement services and solutions. |
DCA (RAG) | Amber/Green |
DCA text: | The Infrastructure Project Authority's Delivery Confidence Assessment rating is Amber/Green.This is primarily due to the following factors: The Next Generation Communications Network programme is currently in the Concept Phase and it's Strategic Outline Case Outletter was received in April 2021. The programme team will be submitting a detailed Outline Business Casein October 2021 that will lay out firm objectives, and evidenced views on choices, preferred options, commercial strategy, costs and scope. |
Start date | 2021-03-31 |
End date | 2031-03-31 |
Schedule text | The project end-date is 31 March 2031. This is primarily due to the following factors: The Next Generation Communications Network programme is currently in the Concept Phase and it's Strategic Outline Case Outletter was received in April 2021. The programme team will be submitting a detailed Outline Business Casein October 2021 that will lay out firm objectives, and evidenced views on the programmes choices, preferred options, commercial strategy, costs and scope. |
Baseline | £0.00m |
Forecast | £0.00m |
Variance | 0.00% |
Variance text: | The Next Generation Communications Network programme is currently in the Concept Phase and it's Strategic Outline Case Outletter was received in April 2021. The programme team will be submitting a detailed Outline Business Case in October 2021 that will lay out firm objectives, and evidenced views on the programmes choices, preferred options, commercial strategy, costs and scope. Therefore no cost data present at this stage. |
Whole Life Cost | £0.00m |
WLCost text: | The Next Generation Communications Network programme is currently in the Concept Phase and it's Strategic Outline Case Outletter was received in April 2021. The programme team will be submitting a detailed Outline Business Case in October 2021 that will lay out firm objectives, and evidenced views on the programmes choices, preferred options, commercial strategy, costs and scope. Therefore no whole life cost data at this stage. |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2021.csv |