Description: The A400M Programme is intended to deliver and support ATLAS aircraft into service which are capable of: - Operating in domestic and international air environments, including contested air, to well-found and remote bases and airstrips. - The inter- and intra-theatre deployment, sustainment and recovery of passengers and freight. - Providing an aerial delivery capability in order to airdrop personnel and freight to the point of need. - Providing inter- and intra-theatre aeromedical movement of casualties. - Providing fixed-wing support to Standing Home Commitments and Contingent Overseas Operations, consistent with Defence Commitments' direction in support of specialist users.
DCA (RAG) Amber
DCA text: Compared to financial year 19/20-Q2, the Infrastructure Project Authority's Delivery Confidence Assessment rating remained at Amber. This is primarily due to the following factors: The Senior Responsible Owner's current Delivery Confidence Assessment is Amber. The Senior Responsible Owner considers availability (the provision of aircraft ready to be tasked and flown) to be the most important indicator of Programme health. This has increased steadily over the last 12 months under the continued watch of the Joint Venture Steering Group. The Programme still suffers from periods of downturn, is able to react and recover when they occur. The need for continued close attention drives the Amber assessment but there are no long-term concerns. More specifically on Capability Delivery Confidence, new milestones are coming along with increasing confidence of success. Natural Surface Operations graduated to the front line in April 21; Freefall Para trials are underway. The first Tactical Course is planned to finish in September, which will culminate the graduation of further elements of Tactical Capability at the end of the year.
Start date 2000-05-17
End date 2024-03-31
Schedule text Compared to financial year 19/20-Q2, the project's end-date remained scheduled to finish on 31 MAR 2024.
Baseline £191.48m
Forecast £181.44m
Variance -5.00%
Variance text: The budget variance exceeds 5%. Variance is over 5% of underspend and this is as a result of the savings measures exercises.
Whole Life Cost £3,783.03m
WLCost text: Compared to financial year 19/20-Q2, the projects Baseline Whole Life Cost increased from £3356.23m to £3783.03m. This is primarily due to the following factors: Costs reflect financial estimate to the point of equipment delivery in March 2024
Notes1:
Notes2:
Sourcefile IPA_2021.csv

Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories


Acknowledgement: GMPP data has been re-used under the Open Government Licence.