2021 Report details for project: A400M
Project name | A400M - there are 11 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022, 2023 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | MOD (D17 ) - see all reports for this organisation |
Report year | 2021 (data is from March 2021) |
Category | Military - see all reports for this category |
Description: | The A400M Programme is intended to deliver and support ATLAS aircraft into service which are capable of: - Operating in domestic and international air environments, including contested air, to well-found and remote bases and airstrips. - The inter- and intra-theatre deployment, sustainment and recovery of passengers and freight. - Providing an aerial delivery capability in order to airdrop personnel and freight to the point of need. - Providing inter- and intra-theatre aeromedical movement of casualties. - Providing fixed-wing support to Standing Home Commitments and Contingent Overseas Operations, consistent with Defence Commitments' direction in support of specialist users. |
DCA (RAG) | Amber |
DCA text: | Compared to financial year 19/20-Q2, the Infrastructure Project Authority's Delivery Confidence Assessment rating remained at Amber. This is primarily due to the following factors: The Senior Responsible Owner's current Delivery Confidence Assessment is Amber. The Senior Responsible Owner considers availability (the provision of aircraft ready to be tasked and flown) to be the most important indicator of Programme health. This has increased steadily over the last 12 months under the continued watch of the Joint Venture Steering Group. The Programme still suffers from periods of downturn, is able to react and recover when they occur. The need for continued close attention drives the Amber assessment but there are no long-term concerns. More specifically on Capability Delivery Confidence, new milestones are coming along with increasing confidence of success. Natural Surface Operations graduated to the front line in April 21; Freefall Para trials are underway. The first Tactical Course is planned to finish in September, which will culminate the graduation of further elements of Tactical Capability at the end of the year. |
Start date | 2000-05-17 |
End date | 2024-03-31 |
Schedule text | Compared to financial year 19/20-Q2, the project's end-date remained scheduled to finish on 31 MAR 2024. |
Baseline | £191.48m |
Forecast | £181.44m |
Variance | -5.00% |
Variance text: | The budget variance exceeds 5%. Variance is over 5% of underspend and this is as a result of the savings measures exercises. |
Whole Life Cost | £3,783.03m |
WLCost text: | Compared to financial year 19/20-Q2, the projects Baseline Whole Life Cost increased from £3356.23m to £3783.03m. This is primarily due to the following factors: Costs reflect financial estimate to the point of equipment delivery in March 2024 |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2021.csv |