2021 Report details for project: CHIEF Transition Programme
Project name | CHIEF Transition Programme - there is only one report for this project |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | HMRC (D25) - see all reports for this organisation |
Report year | 2021 (data is from March 2021) |
Category | ICT - see all reports for this category |
Description: | The CHIEF Transition Programme ensured that Customs Handling of Import Export Freight (CHIEF) was able to operate effectively alongside Customs Declaration Services (CDS) future platform for all customs declarations when the Transition Period ended in December 2020, and it will continue for up to a further five years if required. Under the dual platform strategy, CDS will handle Northern Ireland trade, while CHIEF will handle all other trade. |
DCA (RAG) | Green |
DCA text: | The Infrastructure Project Authority's Delivery Confidence Assessment rating is Green.This is primarily due to the following factors: Following Release 1 delivery being successfully deployed in to live, all activity that was required as part of the cutover to live has been implemented. The CHIEF Transition Programme had a huge success in meeting the objectives of the Business Case, with 300 million declarations in the first year and 400 declarations in the second. Alongside this were the CHIEF Performance and 87 eco systems which were successfully sustained, and the migration and onboarding of declarants between CHIEF and CDS (Customs Declaration Service), to support the dual platform approach for December 2020. Following the successful delivery of release 1, Borders & Trade Delivery Group considered the lessons learned and revised their delivery model and Delivery Directorates have been established that focus on import, export and Transit end to end journeys; and customer strategies that sit across these for traders, hauliers, intermediaries, ports and the rest of the supply chain. |
Start date | 2019-10-23 |
End date | 2021-03-30 |
Schedule text | The project end-date is 30 March 2021. This is primarily due to the following factors: Due to the Borders and Trade re-structure that came into effect on 08/02/2021, CHIEF Transition Programme no longer exists. CHIEF Transition Project Management (PMO) has completed the Closure & Handover Report, Lessons Learned Report and all supporting documents to request that the CHIEF Transition be formally closed down as a Programme with appropriate oversight from the Infrastructure & Projects Authority. |
Baseline | £45.19m |
Forecast | £22.68m |
Variance | -50.00% |
Variance text: | The budget variance exceeds 5%. Reductions in costs were due to revised IT resource spend across specific projects. |
Whole Life Cost | £45.19m |
WLCost text: | The projects Baseline Whole Life Cost is £45.19m. This is primarily due to the following factors: Reductions in costs were due to a reduction in IT resource costs and a change in recruitment strategy. The baseline reflects this position as the programme is now closing, the Whole Life Cost has been reviewed. |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2021.csv |