2021 Report details for project: Securing our Technical Future
Project name | Securing our Technical Future - there are 4 reports for this project: 2020, 2021, 2022, 2023 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | HMRC (D25) - see all reports for this organisation |
Report year | 2021 (data is from March 2021) |
Category | ICT - see all reports for this category |
Description: | The Programme has been established to stabilise and refresh HMRC's current estate which is aged and exiting our 3 data centres the contracts for which expire in 2022 (any further lease extension is against Cabinet Office guidance and likely to prompt wider Commercial challenge) and readying the estate for a move to the new destination platforms, Cloud and Crown Hosting (for physical assets). |
DCA (RAG) | Amber |
DCA text: | Compared to financial year 19/20-Q2, the Infrastructure Project Authority's Delivery Confidence Assessment rating remained at Amber. This is primarily due to the following factors: The DCA remains amber because during 2020, SoTF has been impacted by delays caused by Covid-19 and EU-Exit. Additionally, there has been a significant change in the need to exit a data centre 12 months earlier than expected. The challenges come at a time when there is significant change in leadership with the Programme Director leaving. However, the programme acted swiftly and pragmatically in appointing a replacement. |
Start date | 2018-04-01 |
End date | 2022-06-30 |
Schedule text | Compared to financial year 19/20-Q2, the project's end-date remained scheduled to finish on 30 June 2022 This is primarily due to the following factors: The programme is currently on schedule and it is expected to stay on schedule. |
Baseline | £69.68m |
Forecast | £57.88m |
Variance | -17.00% |
Variance text: | The budget variance exceeds 5%. The main areas contributing to the 20/21 underspend are; the 3 month COVID pause and the reduction of dual run/run costs required this year, due to the delay in migrations, which have now been reprofiled into the later years. |
Whole Life Cost | £312.06m |
WLCost text: | Compared to financial year 19/20-Q2, the projects Baseline Whole Life Cost remained at £312.06m. This is primarily due to the following factors: The whole life costs have remained stable and are expected to through to Programme completion. We have recently refreshed the Programme Business case and remain confident that we will deliver within the funding envelope. We have changed the migration plan to accelerate the exit out of a data centre, as plans progress, we will continue to monitor and revisit this area as required. |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2021.csv |