2021 Report details for project: Evolve

Project name Evolve - there is only one report for this project
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation DFE (D6) - see all reports for this organisation
Report year 2021 (data is from March 2021)
Category Transformation - see all reports for this category
Description: The Evolve portfolio is an enterprise wide transformation which enables SLC's corporate strategy. The strategy has 5 key objectives: An Outstanding Customer Experience; An Enabler of Opportunity; Leaner, Better, Doing more for less; A Great place to work; Trusted delivery partner.The portfolio contains a number of programmes that are designed to further enable and enhance how the SLC delivers its services. These programmes include; Customer Engagement Management, Apps and Portals, Data, Policy Commissioning, Accelerated Service Improvement, People, and Working Practices Transformation.
DCA (RAG) Amber
DCA text: The Infrastructure Project Authority's Delivery Confidence Assessment rating is Amber.This is primarily due to the following factors: We have made good progress in delivering sizeable amount of change to the business and its systems, against very tight timescales. We are now in a critical phase of delivery with no scope for adding contingency to the timescale which is why we have given our own assessment of delivery confidence as Amber/Red.
Start date 2019-10-01
End date 2022-09-30
Schedule text The project end-date is 30 September 2022. This is primarily due to the following factors: No significant changes to critical path in Q4 for 20-21.
Baseline £37.52m
Forecast £34.78m
Variance -7.00%
Variance text: The budget variance exceeds 5%. In year spend variance reflects the reprioritisation of funding which has moved deliverables into FY 21-22. This is offset to an extend by additional costs within the CEM programme due to complexities of Data integration and Migration. DfE de-prioritised initiatives due to budget constraints and covid.
Whole Life Cost £146.29m
WLCost text: The projects Baseline Whole Life Cost is £146.29m. This is primarily due to the following factors: Budget agreed on an annual basis with the Sponsor department Department for Education (DfE).
Notes1:
Notes2:
Sourcefile IPA_2021.csv