2021 Report details for project: T Level Programme

Project name T Level Programme - there are 5 reports for this project: 2019, 2020, 2021, 2022, 2023
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation DFE (D6) - see all reports for this organisation
Report year 2021 (data is from March 2021)
Category Transformation - see all reports for this category
Description: To increase the economic value of skills being supplied by the post 16 system, increasing take-up of high quality qualifications to improve skills, increasing productivity and social mobility. To enable the sustainable delivery of new high quality T Levels for 16-19 year olds.
DCA (RAG) Amber/Red
DCA text: Compared to financial year 19/20-Q2, the Infrastructure Project Authority's Delivery Confidence Assessment rating remained at Amber/red. This is primarily due to the following factors: The IPA made seven recommendations to improve the project and programme management of the T Level delivery for larger successive waves. We have made significant progress in addressing all the recommendations and meet on a monthly basis with the IPA to keep them informed of the progress we are making. The Technical Education Reform Board are sighted at bi-monthly intervals, on the progress we are making. The Major Projects Team at DfE have also provided us with additional support to ensure we remain on track to deliver T Levels in future waves. We will be carrying out our own internal review of the progress made against the assurance of action plan in June 2021.
Start date 2016-10-25
End date 2023-09-30
Schedule text Compared to financial year 19/20-Q2, the project's end-date remained scheduled to finish on 30 September 2023 This is primarily due to the following factors: The current schedule has no known deviations from the planned schedule. Lessons learned from Wave 1 roll out are in progress to support planning for future waves. Covid-19 introduced new levels of uncertainty and the team are monitoring the potential impact on launch in September 2021.
Baseline £259.61m
Forecast £143.84m
Variance -45.00%
Variance text: The budget variance exceeds 5%. We are forecasting an underspend against the 20-21 budget. This underspend has emerged primarily due to the impact of Covid on the programme throughout the year.
Whole Life Cost £1,101.26m
WLCost text: Compared to financial year 19/20-Q2, the projects Baseline Whole Life Cost increased from £155.60m to £1101.26m. This is primarily due to the following factors: Our current projected Whole Life Costs has been refined in the course additional planning through spending review. Covid has had a considerable impact in FY 20-21
Notes1:
Notes2:
Sourcefile IPA_2021.csv