2021 Report details for project: Apprenticeships Reform Programme
Project name | Apprenticeships Reform Programme - there are 5 reports for this project: 2017, 2018, 2019, 2020, 2021 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | DFE (D6) - see all reports for this organisation |
Report year | 2021 (data is from March 2021) |
Category | Transformation - see all reports for this category |
Description: | To create more high quality apprenticeships, meet the skills needs of employers and the country, to create progression for apprentices and to widen participation and social mobility in apprenticeships. |
DCA (RAG) | Green |
DCA text: | Compared to financial year 19/20-Q2, the Infrastructure Project Authority's Delivery Confidence Assessment rating decreased from Amber/Red to Green. This is primarily due to the following factors: The final elements of the reform programme are now in place. |
Start date | 2015-05-08 |
End date | 2021-04-01 |
Schedule text | Compared to financial year 19/20-Q2, the project's end-date remained scheduled to finish on 01 April 2021 This is primarily due to the following factors: The final elements of the reform programme are now in place, having been delivered by the project end date. |
Baseline | £2,675.20m |
Forecast | £1,899.48m |
Variance | -29.00% |
Variance text: | The budget variance exceeds 5%. The baseline was set in 2015 which was before the Levy transformation was implemented. This budget is very difficult to forecast as there is a lot of uncertainty around employer behaviour following the introduction of the new levy. Starts delivered since introduction of the Levy in May 2017 continue to be lower than expected. Employer behaviour is hard to predict and it is very difficult to accurately forecast spend during a period of such uncertainty. Our updated costs for 2020-21 reflects the reduction in the number of starts. The figures for 2020-21 are the draft year end position and are still subject to final review and audit. |
Whole Life Cost | £11,347.50m |
WLCost text: | Compared to financial year 19/20-Q2, the projects Baseline Whole Life Cost increased from £11347.41m to £11347.50m. This is primarily due to the following factors: The baseline whole life costs have not changed from 19-20 and has remained at 11347.50 (£m). 11347.41 was reported in 19/20 due to a reporting error which resulted in an immaterial decrease in the baseline. This has now been corrected. |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2021.csv |