2020 Report details for project: Census Transformation Programme
| Project name | Census Transformation Programme - there are 6 reports for this project: 2016, 2017, 2018, 2019, 2020, 2021 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | ONS (D303 ) - see all reports for this organisation |
| Report year | 2020 (data is from September 2019) |
| Category | Transformation - see all reports for this category |
| Description: | Delivering a successful 2021 Census, researching how to make it the last of its kind and transforming the work of ONS in how we collect, process and analyse data. |
| DCA (RAG) | Amber |
| DCA text: | The IPA Delivery Confidence Assessment (DCA) rating at Q2 1920 (30th September 2019) was Amber, which has not changed since last year's Q2 1819 Amber, due primarily to the following factors; - The focus of the programme at Q2 1819 was on readiness for on-boarding suppliers and completing service integration activities. These challenges were worked through successfully and replaced with fresh challenges, such as readiness for Rehearsal. The programme will continue to carry a level of risk in the short/medium term. - Despite much collaboration with other government departments the programme is still experiencing delays to the receipt of admin data. Teams are implementing contingencies and workarounds to continue with the transformation of statistics and supporting the Census in the meantime. Since the Q2 1920 (30th September 2019) Amber IPA DCA, the following non-project operating environment activities have impacted the original Q2 IPA DCA; - Impact and delay to the mandatory Census legislation due to the prioritisation of the political situation at the time- EU Exit and the early General Election. ONS are working closely with Cabinet Office colleagues to progress at pace. Since the Q2 1920 (30th September 2019) Amber IPA DCA, the following primary project actions have impacted the original Q2 IPA DCA; - No actions have impacted the original Q2 IPA DCA narrative. |
| Start date | 2015-01-01 |
| End date | 2025-03-31 |
| Schedule text | The scheduled baseline project end date at Q2 1920 (30th September 2019) is 31/03/25, has not changed since last year's Q2 1819 date of 31/03/25, due primarily to the following factors; - Plans continue to run to schedule and there have been no factors which would impact the baseline project end date. - Business case approval by HM Treasury in July 2019, with a baseline end date of March 2025. Since the Q2 1920 (30th September 2019) baseline project end date of 31/03/25, the following non-project operating environment activities have impacted the original Q2 baseline project end date; - N/A - No activates have impacted the original Q2 IPA DCA end date. Since the Q2 1920 (30th September 2019) baseline project end date of 31/03/25, the following primary project actions have impacted the original Q2 baseline project end date; - N/A - No actions have impacted the original Q2 IPA DCA end date. |
| Baseline | £141.52m |
| Forecast | £141.52m |
| Variance | None% |
| Variance text: | Budget variance less than 5% |
| Whole Life Cost | £905.59m |
| WLCost text: | The baseline Whole Life Cost at Q2 1920 (30th September 2019) is £905.59m, has decreased by £0.91m since last year's Q2 1819 (£m) baseline Whole Life Cost of £906.50m, due primarily to the following factors; - The costs provided in 2Q 1920 reflect the Census & Data Collection Transformation costs aligned to the Full Business Case that was submitted to HM Treasury and approved 31 July 2019. The review of the costs carried out in the preparation of the FBC resulted in the £0.91 decrease. - No other factors impacted the Whole Life Cost. Since the Q2 1920 (30th September 2019) £905.59m baseline Whole Life Cost, the following non-project operating environment activities have impacted the original baseline Q2 Whole Life Cost; - No non-project operating environment activities have impacted the original Q2 baseline Whole Life Cost. Since the Q2 1920 (30th September 2019) £905.59m baseline Whole Life Cost, the following primary project actions have impacted the original Q2 baseline Whole Life Cost; - No primary project actions have impacted the original Q2 baseline Whole Life Cost. |
| Notes1: | Was Census & Data Collection Transformation Programme |
| Notes2: | |
| Sourcefile | IPA_2020.csv |