2020 Report details for project: Astute Boats 1-7

Project name Astute Boats 1-7 - there are 11 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022, 2023
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation MOD (D17 ) - see all reports for this organisation
Report year 2020 (data is from September 2019)
Category Military - see all reports for this category
Description: The design, development and manufacture of Astute class submarines.
DCA (RAG) Amber/Red
DCA text: The IPA Delivery Confidence Assessment (DCA) rating at Q2 1920 (30th September 2019) was Amber/Red, which has declined since last year's Q2 1819 Amber, due primarily to the following factors; - A delay to Boat 4 which was caused by emergent technical issues which required unplanned repair and rework before proceeding with the normal commissioning process. - Elements of work on Boat 5 were paused in order to deploy extra resource to resolving the issues on Boat 4, impacting on the delivery. Through additional recruitment and provision of training to upskill the current workforce, we will significantly improve the situation in the medium term. Since the Q2 1920 (30th September 2019) Amber/Red IPA DCA, the following primary project actions have impacted the original Q2 IPA DCA; - The MOD has worked with its Tier 1 industrial partners to deliver Boat 4 to the Royal Navy and to recover the Boat 5 schedule, as well as improve production quality. Normal boat commissioning operations are now progressing.
Start date None
End date None
Schedule text Exempt under Section 24 of Freedom of Information Act 2000 (National Security)
Baseline £467.43m
Forecast £424.11m
Variance -0.09%
Variance text: The 19/20 in-year baseline / forecast variance at Q2 1920 (30th September 2019) of -9%, is due primarily to the following factors; - Greater clarity of expenditure across the Boat Build Programme. Since the Q2 1920 (30th September 2019) 19/20 in-year baseline / forecast variance of -9%, the following primary project actions have impacted the original Q2 19/20 in-year variance; - Boat 4 has been successfully delivered from Barrow. - Through continued close engagement and collaboration with industry further schedule improvement has been made.
Whole Life Cost £10,769.42m
WLCost text: The baseline Whole Life Cost at Q2 1920 (30th September 2019) is £10,769.42m, has increased by £798.65m since last year's Q2 1819 (£m) baseline Whole Life Cost of £9,970.77m, due primarily to the following factors; - The department re-baselined the ASTUTE programme for the long term, with its associated whole life costs, as our understanding of the overall schedule and costs matured. Approval changes across the whole programme including boats, schedules, rates, and performance expectation. None of which are not attributable to a discrete boat or cause
Notes1:
Notes2:
Sourcefile IPA_2020.csv