2020 Report details for project: 700 MHz Clearance Programme
Project name | 700 MHz Clearance Programme - there are 5 reports for this project: 2017, 2018, 2019, 2020, 2021 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | DCMS (D5 ) - see all reports for this organisation |
Report year | 2020 (data is from September 2019) |
Category | Infrastructure - see all reports for this category |
Description: | Investing up to £600m to clear the 700MHz spectrum by mid-2020 for use for mobile broadband services in the future. |
DCA (RAG) | Amber/Green |
DCA text: | The IPA Delivery Confidence Assessment (DCA) rating at Q2 1920 (30th September 2019) was Amber/Green, which has improved since last year's Q2 1819 Amber, due primarily to the following factors; - The Delivery Confidence Assessment at Q2 reflected the uncertainty of a general election and the impact this might have on the timeline. |
Start date | 2015-01-13 |
End date | 2022-01-01 |
Schedule text | The scheduled baseline project end date at Q2 1920 (30th September 2019) is 01/01/22, has not changed since last year's Q2 1819 date of 01/01/22, due primarily to the following factors; - The scheduled end date of the clearance events was May 2020, however the COVID-19 outbreak has impacted the final two events. Engineering work will continue as the programme approaches closure. |
Baseline | £156.00m |
Forecast | £94.20m |
Variance | -0.40% |
Variance text: | The 19/20 in-year baseline / forecast variance at Q2 1920 (30th September 2019) of -40%, is due primarily to the following factors; - The programme has identified whole life savings against the SR2015 Funding Profile of over £200m and forecast costs have been reprofiled to reflect the current requirements. - Budget savings have been made against all areas of delivery specifically the infrastructure clearance, viewer support and PMSE costs. Since the Q2 1920 (30th September 2019) 19/20 in-year baseline / forecast variance of -40%, the following non-project operating environment activities have impacted the original Q2 19/20 in-year baseline / forecast variance; - The COVID-19 virus has caused the infrastructure programme to be delayed, extending the viewer support programme and slipping some costs into 2020-21. |
Whole Life Cost | £595.00m |
WLCost text: | The baseline Whole Life Cost at Q2 1920 (30th September 2019) is £595.00m, has increased by £0.08m since last year's Q2 1819 (£m) baseline Whole Life Cost of £594.92m, due primarily to the following factors; - The increase is due to rounding . |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2020.csv |
Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories