2019 Report details for project: PROTECTOR
| Project name | PROTECTOR - there are 7 reports for this project: 2017, 2018, 2019, 2020, 2021, 2022, 2023 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | MOD (D17) - see all reports for this organisation |
| Report year | 2019 (data is from September 2018) |
| Category | Military - see all reports for this category |
| Description: | The PROTECTOR Programme will deliver a future UK capability for deep and persistent armed surveillance, target acquisition, and reconnaissance. |
| DCA (RAG) | Amber/Red |
| DCA text: | Financial Review, rebaselining and contract re-negotiations are concluded. Review note is pending approval. New Mandate to be issued in due course. Programme will deliver 2 yrs late and over original predicted cost. |
| Start date | 2009-04-30 |
| End date | 2035-03-31 |
| Schedule text | The re-baselined programme has caused a delay of Interim Operating Capability to Nov 2023 and Full Operating Capability to October 2025. |
| Baseline | £64.24m |
| Forecast | £52.72m |
| Variance | -18.00% |
| Variance text: | Variance attributable to increase in Joint Forces Command Infrastructure costsings and movement in the foreign exchange market rate. |
| Whole Life Cost | £1,039.25m |
| WLCost text: | Joint Forces Command confirm that Programme is affordable. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2019.csv |