2019 Report details for project: Washington Embassy Refurbishment

Project name Washington Embassy Refurbishment - there are 3 reports for this project: 2019, 2020, 2021
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation FCO (D13) - see all reports for this organisation
Report year 2019 (data is from September 2018)
Category Infrastructure - see all reports for this category
Description: Refurbishment and upgrading of key buildings on our Washington, USA, compound. These buildings currently fail to fully meet health and safety requirements. Further investment in modernising these buildings will futureproof our abiliy to deliver effective diplomatic and operational solutions in our most important global post.
DCA (RAG) Amber
DCA text: The programme continues to make good progress and remains on track. Amber remains the appropriate Delivery Confidence Assessment. Royal Institute of British Architects (RIBA) Stage 3 has now been signed off, the design team are now into RIBA Stage 4 and the procurement process for a contractor is now well underway. Early indications suggest a good level of commercial interest in what is a significant local public sector contract, however, proof of the pudding will be in the quality of final bids. Suggest that the Delivery Confidence Assessment is reviewed at this point. Programme remains on track for design completion, appointment of preferred bidder and submission of Full Business Case (FBC) approval in Spring '19 (subject to IPA Gateway 3 Review). Work on site by Summer '19, with anticipated completion by end 2021.
Start date 2017-01-01
End date 2022-12-12
Schedule text The programme continues to make good progress and on track for design completion, appointment of preferred bidder and submission of Full Business Case (FBC) approval in Spring '19 (subject to IPA Gateway 3 Review). Work on site by Summer '19, with anticipated completion by end 2021.
Baseline £8.70m
Forecast £8.70m
Variance 0.00%
Variance text: Budget variance less than 5%
Whole Life Cost £63.70m
WLCost text: Baseline has remained consistent during the developed and technical design stages
Notes1:
Notes2:
Sourcefile IPA_2019.csv

Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories


Acknowledgement: GMPP data has been re-used under the Open Government Licence.