2019 Report details for project: 100,000 Genomes Project
Project name | 100,000 Genomes Project - there are 5 reports for this project: 2015, 2016, 2017, 2018, 2019 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | DHSC (D12) - see all reports for this organisation |
Report year | 2019 (data is from September 2018) |
Category | Transformation - see all reports for this category |
Description: | The primary aim of this programme is to deliver the then Prime Minister, David Cameron's, commitment to sequence 100,000 whole human genome samples by December 2018. The Project has four specific aims: to bring benefit to patients and create a genomic medicine service for the NHS; to enable new scientific discovery and medical insights; to create an ethical and transparent programme based on consent; to kick start the development of a UK genomics industry. |
DCA (RAG) | Amber |
DCA text: | The RAG rating reflects the good progress made and clear focus on preparation for transitioning the project into the Genomics Medicine Service. SRO and Programme Director continue to proactively challenge delivery partners (e.g. Genomics England on informatics and NHS England on GMCs providing samples) at the Project Delivery Board. Ministers, No 10 and the IPA understand current status, delivery challenges relating to this world-leading project. |
Start date | 2013-04-10 |
End date | 2018-12-31 |
Schedule text | To fulfil the vision of the Project, we are always working at the edge of known science and as with all scientific research, it takes time to get it right. We have made great progress and are on track to sequence 100,000 genomes by end of Dec 2018. Genomics England and NHS England report that recruitment of the rare disease element of the project is going well. Delivery of the cancer element of the project has been challenging but is improving. |
Baseline | £50.00m |
Forecast | £82.70m |
Variance | 65.00% |
Variance text: | Over the life of the project we have reprofiled the sequencing element, resulting in a higher proportion of the samples being sequenced in 18-19 than originally planned. This does not change the overall cost but reduces spend in the earlier years and increases it in 18-19. |
Whole Life Cost | £369.90m |
WLCost text: | The Budgeted Whole Life Costs is £369.9m for Genomics England and Health Education England (HEE). Some of the anticipated spend for 2017/18 occurs in 2018/19. The increased forecast for 18/19 is due to increased costs associated with developing Genomics Englands elements of the Genomic Medicine Service. |
Notes1: | One Hundred Thousand Genomes Project |
Notes2: | |
Sourcefile | IPA_2019.csv |
Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories