2019 Report details for project: M20 Lorry Area
Project name | M20 Lorry Area - there are 3 reports for this project: 2017, 2018, 2019 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | DFT (D9) - see all reports for this organisation |
Report year | 2019 (data is from September 2018) |
Category | Infrastructure - see all reports for this category |
Description: | The project has been reset and since September 2018 has left the Government Major Projects Portfolio. The project is a study into options for a permanent solution or solutions into the freight management and lorry parking in Kent. The project is currently at its initial stage (option identification / selection). |
DCA (RAG) | Amber |
DCA text: | Discussions are ongoing with the Department on the scope, baseline schedule and budget for the next phase of works. |
Start date | 2015-11-01 |
End date | 2023-07-01 |
Schedule text | The project in its original form (Stanford West Lorry Park) was cancelled on legal advice in November 2017 and £5m allocated for historic blight costs and to develop options for alternative solutions to lorry parking in Kent. This included investigations looking at permanent infrastructure as well as technology solutions. A public information exercise was undertaken. Discussions are ongoing with the Department to establish the scope for the next stage of this project, when agreed funding will be sought to take this forward. |
Baseline | £0.00m |
Forecast | £3.70m |
Variance | 0.00% |
Variance text: | Baseline figures are yet to be approved for the new project. This will be set when the scope is agreed with the Department. The forecast 2018/2019 figure refers to the £5m budget allocated from the closure of the Stanford West project, as of September 2018. |
Whole Life Cost | £0.00m |
WLCost text: | The only funding available for this project was the £5m allocated on the closure of the Sandford West scheme. This funding is now spent and discussions on scope and budget for the next phase of works are ongoing with the Department. |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2019.csv |