2019 Report details for project: Great Western Route Modernisation (GWRM)
Project name | Great Western Route Modernisation (GWRM) - there are 5 reports for this project: 2017, 2018, 2019, 2020, 2021 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | DFT (D9) - see all reports for this organisation |
Report year | 2019 (data is from September 2018) |
Category | Infrastructure - see all reports for this category |
Description: | An extensive programme to modernise existing infrastructure on the Great Western mainline. It will create faster and more reliable services, better stations and increased freight capacity. |
DCA (RAG) | Amber/Red |
DCA text: | The IPA rated this project with an Amber/Red delivery confidence in Q2 17/18. Actions are in place to manage and monitor implementation of recommendations supporting delivery of electrification programme and increased integration of work streams delivering December 19 enhanced timetable. |
Start date | 2011-12-01 |
End date | 2024-12-31 |
Schedule text | The Great Western Route Modernisation programme has delivered electrification from Paddington to Bristol Parkway and Newbury by December 2018, Chippenham by April 2019 and will complete with electrification to Cardiff by November 2019. This will enable the introduction of the enhanced timetable in December 2019 to deliver significant journey time benefits via new trains and infrastructure. Electrification to Cardiff is expected to be completed by January 2020 and project end date by December 2024. |
Baseline | £655.00m |
Forecast | £769.00m |
Variance | 17.00% |
Variance text: | At September 2018, forecast was overestimating the amount of enhancement work that would be completed within 2018-19. Forecasting has since been refined to exclude work now rescheduled for 2019-20 (particularly electrification to Cardiff which will be completed in November 2019) and by March 2019 overall annual Programme spend was within 2% of budget. |
Whole Life Cost | £5,001.00m |
WLCost text: | Over half of overall Programme costs are to fund the electrification of Paddington to Cardiff, with remaining spend on enabling work e.g. platform extensions, line improvements, station capacity. Baseline spend has been reduced by around £420m due to decision not to electrify Cardiff-Swansea section. |
Notes1: | Great Western Route Modernisation |
Notes2: | |
Sourcefile | IPA_2019.csv |