2019 Report details for project: Government Office Hubs Programme
| Project name | Government Office Hubs Programme - there are 7 reports for this project: 2016, 2017, 2018, 2019, 2020, 2021, 2022 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | CO (D2) - see all reports for this organisation |
| Report year | 2019 (data is from September 2018) |
| Category | Transformation - see all reports for this category |
| Description: | The Hubs programme will consolidate and modernise the Governments office estate, creating an office network that supports smarter working and great places to work. |
| DCA (RAG) | Amber |
| DCA text: | Phase 2 delivery timelines have been reviewed with actions put in place to address schedule delays. |
| Start date | 2015-05-01 |
| End date | 2036-03-31 |
| Schedule text | Programme as a whole remains on schedule with individual project timelines and programme tranche timelines shifting in line with emerging priorities and challenges. |
| Baseline | £111.41m |
| Forecast | £111.41m |
| Variance | 0.00% |
| Variance text: | Budget variance less than 5% |
| Whole Life Cost | £564.10m |
| WLCost text: | Budgeted whole life costs are aligned to the latest approved PBC and have remained unchanged for 18/19. |
| Notes1: | Government Hubs Programme |
| Notes2: | |
| Sourcefile | IPA_2019.csv |