2019 Report details for project: Common Technology Services
| Project name | Common Technology Services - there are 4 reports for this project: 2018, 2019, 2020, 2021 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | CO (D2) - see all reports for this organisation |
| Report year | 2019 (data is from September 2018) |
| Category | Transformation - see all reports for this category |
| Description: | Lead the implementation of common technology across government, and by doing so enable civil service transformation and realise better value on IT spend in government. The programme was reset in March 2017 and is now focussed around three core areas: 1. Developing a common approach to common technology: patterns and standards for core technology components, developed in partnership with Departments. 2. Technology delivery to Government Hubs: supporting Government Property Agency with delivery of shared networking infrastructure to the Canary Wharf Hub, including producing a design pattern for future hubs. 3. Networks for government: including operation of the current Public Services Network (PSN) serving over 700 organisations, delivery of Government's future networking approach and helping organisations transition away from existing PSN services which are reaching end of life. |
| DCA (RAG) | Amber |
| DCA text: | The programme is broadly on track to realise its expected benefits, with one area (GovPrint) requiring extra focus in the coming quarters to achieve greater clarity on its deliverables and benefits. |
| Start date | 2016-04-01 |
| End date | 2020-03-31 |
| Schedule text | The programme remains on course to be completed on schedule. |
| Baseline | £8.10m |
| Forecast | £5.20m |
| Variance | -36.00% |
| Variance text: | Lower number of staff and contactors working on the programme so costs are lower than baseline. |
| Whole Life Cost | £43.96m |
| WLCost text: | Reduced scope of programme has led to lower cost against baseline. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2019.csv |