2019 Report details for project: New Polar Research Vessel
| Project name | New Polar Research Vessel - there are 8 reports for this project: 2016, 2017, 2018, 2019, 2020, 2021, 2022, 2023 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | BEIS (D1198) - see all reports for this organisation |
| Report year | 2019 (data is from September 2018) |
| Category | Infrastructure - see all reports for this category |
| Description: | NERC/British Antarctic Survey has a business need to replace its two aging science/logistics support vessels with a new dual role purpose vessel. The FBC calculated that the NPV of the option selected as best overall Value For Money, (design, build operate a new dual role science/logistics support vessel) resulting in a saving of £102m over a period of 25 years representing the anticipated lifetime of the new asset. The reduction in vessel capacity and attendant running costs is predicted to deliver significant savings with only a minor impact of delivery of science days at sea. The Specification/Statement Of Requirements for the new vessel was developed in consultation with the key stakeholders including, but not limited to, the scientific user community; logistics support staff within the British Antarctic Survey and the Supply Side. Working with the selected shipyard, Cammell Laird we are optimising the design and on track to deliver the vessel in Q4 2017/18. NERC is not purchasing any steel. Steel purchased by the main contractor has due regard for the guidance and commercial best practice. |
| DCA (RAG) | Amber |
| DCA text: | The IPA project rating is Amber and action is underway against all recommendations identified and progressing well. There is a monthly call between the Programme Team and IPA to discuss the supporting action plan to complete the recommendations. |
| Start date | 2014-05-01 |
| End date | 2022-12-31 |
| Schedule text | Programme remains on schedule to end in 2022. |
| Baseline | £113.00m |
| Forecast | £111.00m |
| Variance | -2.00% |
| Variance text: | Budget variance less than 5% |
| Whole Life Cost | £1,403.00m |
| WLCost text: | The whole life costs represents costs until 2043/44. These cost include the project costs until closure and recurring Antarctic Partition and Logistics infrastructure budget costs. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2019.csv |