2013 Report details for project: Beyond 2011

Project name Beyond 2011 - there are 3 reports for this project: 2013, 2014, 2015
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation ONS (D303) - see all reports for this organisation
Report year 2013 (data is from September 2012)
Category Transformation - see all reports for this category
Description: Current phase - To recommend the best way to provide populations and small area socia-demographic statistics in the future
DCA (RAG) Amber/Green
DCA text: The programme remains on plan to publish an Option Assessment Report
Start date 2011-04-01
End date 2015-03-31
Schedule text The Programme remains on track to deliver on schedule.
Baseline £5.00m
Forecast £5.75m
Variance 15.00%
Variance text: Variance due to re-profiling the programme budget across financial years. No increase in total Programme budget.
Whole Life Cost £25.00m
WLCost text: Phase 1 will deliver a full business case for phase 2 within whole life costs
Notes1: Beyond 2011 Programme
Notes2:
Sourcefile ONS_2013.csv