2013 Report details for project: Logistics Commodities Services Transformation
Project name | Logistics Commodities Services Transformation - there are 6 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | MOD (D17) - see all reports for this organisation |
Report year | 2013 (data is from September 2012) |
Category | Military - see all reports for this category |
Description: | LCS(T) aims to deliver a future operating model which ensures that procurement processes, inventory management, storage and distribution of non explosive materiel adopts two core fundamentals as mandated by the Defence Board: Certainty of Military Supply and Cost Minimisation, thus delivering value for money. |
DCA (RAG) | Amber |
DCA text: | The Project Team continue to develop documentation for Industry engagement, and to satisfy MOD and HMT scrutiny requirements. Active engagement with HMT has resulted in recent approval to proceed to the Pre-Qualification Questionnaire (PQQ) stage. Availability of funding for failing infrastructure and potential new build is being addressed through the projects assessment phase. |
Start date | 2011-08-01 |
End date | 2018-02-01 |
Schedule text | The Official Journal of the European Union contract notice was issued in February 2013. Subsequently, Cabinet Office and HMT have requested a feasibility study on the early delivery of a new build facility in order to realise benefits and savings during FY15/16. This has delayed the planned Industry Day and release of Pre-Qualification Questionaire. A Review Note is being presented to IAC shortly and industry engagement will re-commence once HMT has approved this. |
Baseline | £8.36m |
Forecast | £8.36m |
Variance | 0.00% |
Variance text: | |
Whole Life Cost | £2,056.19m |
WLCost text: | No significant change. It should be noted that in September 2012 the report encompassed the wider programme, MOSAIC. Following discussions it was agreed that reporting should focus on the main transformation project LCS(T). Some small elements of MOSAIC have since been removed from the cost data e.g. Disposal Services Agency and British Forces Post Office. |
Notes1: | |
Notes2: | |
Sourcefile | MOD_2013.csv |
Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories
Acknowledgement: GMPP data has been re-used under the Open Government Licence.