2013 Report details for project: Puma Helicopter Life Extension Programme
| Project name | Puma Helicopter Life Extension Programme - there are 4 reports for this project: 2013, 2014, 2015, 2016 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | MOD (D17) - see all reports for this organisation |
| Report year | 2013 (data is from September 2012) |
| Category | Military - see all reports for this category |
| Description: | Puma HC1 provided one third of the Department's medium Support Helicopter fleet. The Out of Service Date (OSD) for the Puma HC1 Helicopter fleet was December 2012, driven by obsolescence of components, safety issues and changed legislative requirements. The Life Extension Programme, which will produce the Puma HC2 with an Out of Service date of 2025, will address these hazards by the installation of a glass cockpit, modern avionics, including a digital automatic flight control system, and new engines. These upgrades will address obsolescence and safety issues and deliver a step change in performance, particularly in hot and high environments and brownout conditions. |
| DCA (RAG) | Amber |
| DCA text: | A usable operational temperate climate capability (Day & Night) in permissive environments will be delivered by Dec 13. |
| Start date | 2009-09-30 |
| End date | 2014-10-31 |
| Schedule text | There are a number of contributing factors to the schedule deviation including: greater than originally expected volumes of remedial work that disrupted both development and production activity; delays in sourcing some critical Government Furnished Equipment; and delays to the development programme caused by technical issues and the loss of key Puma flight test personnel in a fatal helicopter accident. The review note, approved in Apr 13, forecasts IOC for Mar 15. The Puma Project Board accepts this risk-adjusted date, noting that plans are being executed to deliver a limited capability in summer of 2013 and a usable but limited operational capability early in 2014. |
| Baseline | £97.82m |
| Forecast | £89.80m |
| Variance | -8.20% |
| Variance text: | PR12 commitment restrictions and need to contract for changes in capability requirements, subsequent to MG, led to contract re-negotiation with the Prime Contractor. This has resulted in a revised funding profile. |
| Whole Life Cost | £279.28m |
| WLCost text: | The programme remains within the Approved Budgetary Limit (ABL) and is affordable within the PR12 funding provision. |
| Notes1: | |
| Notes2: | |
| Sourcefile | MOD_2013.csv |