2018 Report details for project: IT Transformation Programme

Project name IT Transformation Programme - there are 3 reports for this project: 2015, 2017, 2018
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation NCA (PB558) - see all reports for this organisation
Report year 2018 (data is from September 2017)
Category ICT - see all reports for this category
Description: IT Transformation is one of three programmes that together comprise NCA Transformation, which seeks to move the Agency from a legacy IT estate to a modern environment that will support the NCA's technology and information needs, realising the vision of the programme - “Create a cutting edge technology and information environment that connects, empowers and enhances our officers’ crime fighting capabilities”.
DCA (RAG) Amber
DCA text: Following the ITTP Gateway 2 Review in April, the IPA completed a follow up of Action Plan review in September, The review team noted demonstrable progress had been made against all recommendations resulting in the closure of a number of recommendations. The delivery confidence for extant elements of the programme remains Amber/red. Following approval from IPA that the NCA Change Portfolio will be the sole programme registered with GMPP so all outstanding actions will be managed by the Change Portfolio.
Start date 2016-04-01
End date 2022-07-31
Schedule text The schedule of work remains on track
Baseline £38.80m
Forecast £38.80m
Variance 0.00%
Variance text: Budget variance less than 5%
Whole Life Cost £167.68m
WLCost text: IT Transformation Programme WLC is sub-set of the NCA Transformation Programme WLC, which has reduced by £2.5m since the 2016/17 estimate as a result of efficiencies in actual project identified during the implementation in 2017/18. £1m of this reduction is attributed to the WLC of IT Programme.
Notes1:
Notes2:
Sourcefile IPA_2018.csv

Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories