2018 Report details for project: Astute Boats 1-7
| Project name | Astute Boats 1-7 - there are 11 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022, 2023 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | MOD (D17) - see all reports for this organisation |
| Report year | 2018 (data is from September 2017) |
| Category | Military - see all reports for this category |
| Description: | The design, development and manufacture of up to 7 Astute class submarines. |
| DCA (RAG) | Red |
| DCA text: | Improved Governance brought about by the introduction of the Defence Nuclear Organisation and the Submarine Delivery Agency has started to pay dividends with improved awareness and engagement among stakeholders. The most recent Infrastructure and Projects Authority Projects Assessment Review conducted in February 2018 reports the RAG as Amber. |
| Start date | 1997-03-17 |
| End date | 2024-03-31 |
| Schedule text | Boat 4 has launched and will depart Barrow in 2018. Having conducted a comprehensive cost and risk analysis across the Enterprise, it is intended that approval will be sought to deliver Boats 5-7 at revised but realistic schedules. While broadly stable throughout 17/18, delays to the programme have historically been caused by a combination of factors including Industrial performance and also the late provision of essential components to the Build line (Both Industry and MOD have in the past been liable). The Operational Handover dates sought in the forthcoming Whole Programme Review have been subject to comprehensive Schedule Risk Analysis. |
| Baseline | £541.08m |
| Forecast | £562.62m |
| Variance | 4.00% |
| Variance text: | |
| Whole Life Cost | £9,941.96m |
| WLCost text: | Overall variation to the Whole Life Costs have been influenced by schedule delays, increased labour rates and by an increase of Barrow Build Infrastructure overheads. A Whole Programme re-approval approach in 2018 will deliver an improved assessment of risk management. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2018.csv |