2018 Report details for project: A14 Cambridge to Huntingdon Improvement Scheme

Project name A14 Cambridge to Huntingdon Improvement Scheme - there are 7 reports for this project: 2014, 2015, 2016, 2017, 2018, 2019, 2020
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation DFT (D9) - see all reports for this organisation
Report year 2018 (data is from September 2017)
Category Infrastructure - see all reports for this category
Description: To improve the A14 which is a major national and inter-urban regional transport artery between Cambridge and Huntingdon to relieve congestion and support both national and regional economic growth.
DCA (RAG) Amber
DCA text: The project is on track and to ensure successful, timely delivery of the project, the Project Board continues to monitor progress.
Start date 2012-09-01
End date 2021-09-30
Schedule text The project started construction works in autumn 2016 as planned and the site compound opened in January 2017. The scheme is also on track to be open for traffic by December 2020.
Baseline £414.90m
Forecast £363.90m
Variance -12.00%
Variance text: Variance due to re-profiling to complete earthworks in two seasons.
Whole Life Cost £1,423.80m
WLCost text: Currently the scheme has full funding approval of £1.435bn. The reduction from the previous year is due to driving out efficiencies.
Notes1:
Notes2:
Sourcefile IPA_2018.csv