2017 Report details for project: Queen Elizabeth Programme
| Project name | Queen Elizabeth Programme - there are 8 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | MOD (D17) - see all reports for this organisation |
| Report year | 2017 (data is from September 2016) |
| Category | Military - see all reports for this category |
| Description: | To deliver 2 Queen Elizabeth Class aircraft carriers. |
| DCA (RAG) | Amber |
| DCA text: | The IPA described seeing much progress since the last review, its Amber assessment was based on issues around: HMS Queen Elizabeths First Entry to Portsmouth (FEP); cost clarity; manning requirements; the Common Support Model (CSM) business case and support in the Solent when unable to enter port. These actions are being progressed through the stakeholders and included in Holding to Account discussions. FEP will now be a comparatively low key event with a later ceremonial event. A comprehensive assessment of Programme costs has been produced. Manning is being successfully managed based on continued prioritisation. Plans for support in the Solent will be implemented as we gain experience of operating HMS Queen Elizabeth from her home port. |
| Start date | 1998-12-01 |
| End date | 2023-03-31 |
| Schedule text | Challenges exist within HMS Queen Elizabeths near-term schedule, with technical issues on several systems presenting risk to the Ships Staff Move-on Board and Ready for Sea Date programme milestones. The Ships Company and Aircraft Carrier Alliance are working closely to manage these serials. HMS Prince of Wales schedule has further to run and lessons from HMS Queen Elizabeth are being incorporated. |
| Baseline | £601.84m |
| Forecast | £593.27m |
| Variance | -1.00% |
| Variance text: | Budget Variance less than 5% |
| Whole Life Cost | £7,400.08m |
| WLCost text: | The Q2 estimated increase in cost of building the Carriers remains stable. Additional funding for the 10-year support budget change to operating one ship at Very High Readiness and one at High Readiness is being accounted for within Navy Commands control total. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2017.csv |