2017 Report details for project: Maritime Patrol Aircraft

Project name Maritime Patrol Aircraft - there are 7 reports for this project: 2017, 2018, 2019, 2020, 2021, 2022, 2023
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation MOD (D17) - see all reports for this organisation
Report year 2017 (data is from September 2016)
Category Military - see all reports for this category
Description: To deliver a Maritime Patrol Aircraft (MPA) to provide persistent, responsive, effective and adaptive Military Capabilities in the Under Water, Above Water, Littoral and Land environments.
DCA (RAG) Amber
DCA text: Since the last reporting period, there has been a maturing of the infrastructure plan, with an information note describing the approach to approvals (submitted 9 Dec 16) and leading to a review note to be submitted during Q2 17/18. An ABC17 option has been submitted to align manpower profile to the aircraft delivery schedule, which de-risks the build-up to initial operating capability. The overall programme assessment remains at amber due to the number of challenges, dependencies and uncertainties that lie within the programme.
Start date 2014-07-08
End date 2024-04-01
Schedule text There has been no change to any of the programme milestones or the overall programme schedule. Programme milestones have not been included. The details of the build-up of the MPA force have not been publicly revealed for security reasons.
Baseline £7.37m
Forecast £5.57m
Variance -24.00%
Variance text: Realism applied to forecast
Whole Life Cost £2,132.49m
WLCost text: Whole Life Costs reflect the MGBC remaining within the total.
Notes1:
Notes2:
Sourcefile IPA_2017.csv