2017 Report details for project: UKERP
| Project name | UKERP - there are 5 reports for this project: 2013, 2014, 2015, 2016, 2017 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | FCO (D13) - see all reports for this organisation |
| Report year | 2017 (data is from September 2016) |
| Category | Infrastructure - see all reports for this category |
| Description: | The project supports the wider Cabinet Office strategy of consolidating the HMG Estate in Central London in KCS. The project will deliver savings from 2016/17 in operating costs and promotes Diplomatic Excellence. |
| DCA (RAG) | Amber |
| DCA text: | Exit Review has now taken place and the project received an Amber DCA. Problems encountered by the main contractor in delivering specialist aspects of the design did delay construction delivery, although completion was achieved by end of March 2016. OAB was handed back to GPU on programme and all staff are now based in KCS. |
| Start date | 2011-06-01 |
| End date | 2015-08-01 |
| Schedule text | Construction completion delayed by main contractor |
| Baseline | £0.00m |
| Forecast | £0.50m |
| Variance | None% |
| Variance text: | Delays caused by main contractor in 2015 have meant the FCO has had to draw on the risk allowance to cover costs to the FCO. This means the project has come close to its whole life cost, but is still within it. |
| Whole Life Cost | £65.00m |
| WLCost text: | Whole life costs remain within the approved budget |
| Notes1: | Either zero or no Baseline and/or Forecast |
| Notes2: | |
| Sourcefile | IPA_2017.csv |