2017 Report details for project: ABUJA New Office and Residence

Project name ABUJA New Office and Residence - there are 5 reports for this project: 2013, 2014, 2015, 2016, 2017
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation FCO (D13) - see all reports for this organisation
Report year 2017 (data is from September 2016)
Category Infrastructure - see all reports for this category
Description: To provide a secure modern fit for purpose HMG office compound for both BHC and DFID in Abuja, Nigeria.
DCA (RAG) Amber
DCA text: Amber is appropriate at this stage in the project given the challenges with achieving the required quality of workmanship in Nigeria using local labour. Additional exPat supervision and UK supplier input has been procured to support the main contractor with the remainder of the works and completion of the construction works is now set for end 2016. Subject to fit out, occupation will follow in the first part of 2017
Start date 2011-01-01
End date 2017-12-01
Schedule text On schedule
Baseline £13.40m
Forecast £13.70m
Variance 2.00%
Variance text: Budget variance less than 5%
Whole Life Cost £46.00m
WLCost text: Whole life costs remain as reported in the last annual report and in line with budget approvals.
Notes1:
Notes2:
Sourcefile IPA_2017.csv