2017 Report details for project: National Data Services Development Programme
| Project name | National Data Services Development Programme - there are 2 reports for this project: 2017, 2018 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | DOH (D12) - see all reports for this organisation |
| Report year | 2017 (data is from September 2016) |
| Category | ICT - see all reports for this category |
| Description: | The aim of the Programme is to put in place effective services and activities to facilitate clinical professionals, commissioners and researchers legitimate need to use data to inform decision-making and provide insight into the health and care of Englands citizens. |
| DCA (RAG) | Amber/Red |
| DCA text: | The actions in train are: SRO is leading efforts to achieve system wide consensus on the strategic fit of the programme and delivery scope Work with Cabinet Office colleagues to agree the procurement approach Develop an updated OBC to reflect the outcomes of the above actions Seek approval for discovery and early delivery of components of the service to mitigate the impact of the delay to OBC approva |
| Start date | 2015-02-23 |
| End date | 2020-03-31 |
| Schedule text | The programme met the deadlines for delivery of early works to deploy a prototype Data Landing Platform and to meet the ICO code of anonymisation in September and October 2016 respectively. Procurement and implementation activity is on hold pending approval of the revised OBC. A revised timetable will be produced as part of completing the actions set out above. |
| Baseline | £30.18m |
| Forecast | £30.18m |
| Variance | 0.00% |
| Variance text: | Budget variance less than 5% |
| Whole Life Cost | £167.96m |
| WLCost text: | The programme is being re-cast and the revised OBC will only cover the first phase of the project pending clarity of fit with the proposed new regional architecture. This will reduce the whole life costs presented in the revised case. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2017.csv |