2017 Report details for project: A14 Cambridge to Huntingdon Improvement Scheme
Project name | A14 Cambridge to Huntingdon Improvement Scheme - there are 7 reports for this project: 2014, 2015, 2016, 2017, 2018, 2019, 2020 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | DFT (D9) - see all reports for this organisation |
Report year | 2017 (data is from September 2016) |
Category | Infrastructure - see all reports for this category |
Description: | To improve the A14 which is a major national and inter-urban regional transport artery between Cambridge and Huntingdon to relieve congestion and support both national and regional economic growth |
DCA (RAG) | Amber |
DCA text: | The project is on track and to ensure successful, timely delivery of the project, the Project Board continues to monitor progress. To improve the amber delivery confidences rating all actions given to the project have been completed from the 2016 IPA review. |
Start date | 2012-09-01 |
End date | 2021-09-30 |
Schedule text | The project started construction works in Autumn 2016 as planned and the site compound opened in January 2017. The scheme is also on track to be open for traffic by December 2020 |
Baseline | £106.30m |
Forecast | £131.90m |
Variance | 24.00% |
Variance text: | The variance in 2016/17 was due to an increased target which was agreed due to an accelerated programme for this project in the 16/17 financial year. |
Whole Life Cost | £1,492.30m |
WLCost text: | Currently the scheme has full funding approval of £1,435m. |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2017.csv |
Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories
Acknowledgement: GMPP data has been re-used under the Open Government Licence.