2017 Report details for project: Tate Modern Project
| Project name | Tate Modern Project - there are 5 reports for this project: 2013, 2014, 2015, 2016, 2017 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | DCMS (D5) - see all reports for this organisation |
| Report year | 2017 (data is from September 2016) |
| Category | Infrastructure - see all reports for this category |
| Description: | The New Tate Modern will provide London with a unique public space for a rich collection of international art, combined with educational initiatives for diverse audience groups. The New Tate Modern will significantly enhance the UK's reputation as a major cultural force in the world. |
| DCA (RAG) | Green |
| DCA text: | Final recommendations have been met and programme has now completed. |
| Start date | 2010-01-01 |
| End date | 2016-12-31 |
| Schedule text | Programme has now completed |
| Baseline | £12.90m |
| Forecast | £10.90m |
| Variance | -16.00% |
| Variance text: | The final cost is £2m lower than Baseline. |
| Whole Life Cost | £271.00m |
| WLCost text: | The anticipated final cost is £269m. |
| Notes1: | The Tate Modern Project |
| Notes2: | |
| Sourcefile | IPA_2017.csv |