2017 Report details for project: Tate Modern Project

Project name Tate Modern Project - there are 5 reports for this project: 2013, 2014, 2015, 2016, 2017
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation DCMS (D5) - see all reports for this organisation
Report year 2017 (data is from September 2016)
Category Infrastructure - see all reports for this category
Description: The New Tate Modern will provide London with a unique public space for a rich collection of international art, combined with educational initiatives for diverse audience groups. The New Tate Modern will significantly enhance the UK's reputation as a major cultural force in the world.
DCA (RAG) Green
DCA text: Final recommendations have been met and programme has now completed.
Start date 2010-01-01
End date 2016-12-31
Schedule text Programme has now completed
Baseline £12.90m
Forecast £10.90m
Variance -16.00%
Variance text: The final cost is £2m lower than Baseline.
Whole Life Cost £271.00m
WLCost text: The anticipated final cost is £269m.
Notes1: The Tate Modern Project
Notes2:
Sourcefile IPA_2017.csv